Due to the already experienced reliability, the high production output and the technical expertise, the civil engineering specialist Keller foundations decided in favour of the TRM pile system. A total of 410 TRM piles of type 170 were installed, corresponding to a total length of 15,000 m at a depth of up to 45 m. In addition, geothermal probes were also installed in the course of the pile installation. Christian Wetzlmaier (site management Keller): "With the pile system from TRM, the foundation of the new logistics centre could be successfully implemented in a settlement-sensitive soil with different geotechnical properties, taking into account high settlement requirements."
Due to the good coordination of the executing companies, the deadline milestone for the main work was met and the foundation was completed in only two months.