Expansion and renewal of water supply system for Darkhan city

Already in 2018, TRM received the order for the construction of a drinking water pipeline in Mongolia (Altai) - see also here: https://trm.at/en/pipe/referenzen/altai. After the successful completion of the project in 2021, the second project could be started this year, this time in Darkhan.

In the next 24 months, TRM will implement the project as turnkey contractor for the Mongolian Ministry of Construction and Urban Development (MCUD) and, among others, produce, deliver and install 14 km of drinking water pipeline (ductile iron with diameter DN150 - DN600 with VRS-T connection). TRM is supported by Teamension GmbH (project management), MTU LLC (civil works contractor) and Bernard Gruppe ZT GmbH (supervision). 

The first ductile iron pipes were delivered to Mongolia as early as the beginning of September 2023, allowing the first construction work of the 2-year project to start.

Safe water supply.