Successful completion of the foundation work for the "Swimming pool Hall" project

Good news: The foundation work for the "Swimming pool Hall" has been completed. The entire project comprises the renovation of the "Swimming pool Hall" with the construction of a 50-meter pool and a children's pool.

85 pcs. TRM ductile iron piles ensure the safety of the pools. The foundation is formed by a total length of 1,050m with TRM 118x9.0mm and a 220mm grouted pile shoe.
The flexibility of the TRM Piling System enabled the construction site to be completed quickly and efficiently. It took less than 20 minutes to install the approximately 12m long piles.

Thanks to the excellent cooperation with Hollaus Bau and TRM, the project was successfully completed within a short space of time.